Sign Replacement on CO 72 and CO 74 in Boulder, Jefferson & Gilpin Counties

Project Facts

  • Cost: $300,000
  • Contractor(s): CC Enterprises
  • Location: On CO 72 from mile point (MP) 18.0 to MP 29.3, and on CO 74 from MP 6.8 to 18.1
  • Timeline: through summer 2018

Work this Week
April 1-7

  • Crews will install signs, and do excavation and concrete work.
  • Note that work will be completed from 7 a.m. to 7 p.m., Monday through Friday.

In March 2018, crews started replacing 300 signs on Colorado Highway 72 and 600 signs on Colorado Highway 74 to provide easy-to-read, important information about speed limits, upcoming curves and more. Work is expected to be complete in summer 2018.


Schedule & Traffic Impacts

  • Project hours: 7 a.m. - 7 p.m., Monday through Thursday, with occasional work during these hours on Friday
  • Expect eastbound and westbound shoulder closures and lane closures throughout the project limits.