Sign Replacement on CO 72 and CO 74 in Boulder, Jefferson & Gilpin Counties
Project Facts
- Cost: $300,000
- Contractor(s): CC Enterprises
- Location: On CO 72 from mile point (MP) 18.0 to MP 29.3, and on CO 74 from MP 6.8 to 18.1
- Timeline: through summer 2018
Work this Week
April 1-7
- Crews will install signs, and do excavation and concrete work.
- Note that work will be completed from 7 a.m. to 7 p.m., Monday through Friday.
In March 2018, crews started replacing 300 signs on Colorado Highway 72 and 600 signs on Colorado Highway 74 to provide easy-to-read, important information about speed limits, upcoming curves and more. Work is expected to be complete in summer 2018.
Schedule & Traffic Impacts
- Project hours: 7 a.m. - 7 p.m., Monday through Thursday, with occasional work during these hours on Friday
- Expect eastbound and westbound shoulder closures and lane closures throughout the project limits.