I-70 - Northwestern Colorado Wrong Way Detection
Project complete
About the Project
Starting July 12, the Colorado Department of Transportation and Contractor Colorado Barricade will begin installing wrong-way detection systems in Eagle, Garfield, Mesa, and Summit counties. Work will take place at 87 off-ramp locations along I-70, starting at Exit 205 (Silverthorne) and moving west to complete at Exit 2 (Rabbit Valley).
Project Facts
- Cost: $2.2 Million
- Contractor: Colorado Barricade
- Timeline: July to October 2021
- Location: 87 on/off-ramps along I-70 in Northwestern Colorado, Eagle, Garfield, Mesa and Summit Counties
Project map with start and end mile points