Pueblo County Highway Sign Replacement
Project Complete
About the Project
Crews on this project removed and replaced signs on or above various highways in Pueblo County.
Locations include:
- On CO 45 (Pueblo Boulevard) from E. Spaulding Avenue to Bahama Drive
- CO 47 from I-25 to CO 50
- CO 50 from Baxter Road to Murillo Lane
- CO 50 from Dirt Road to I-25
- I-25 from south of W. Pueblo Boulevard to north of Eagleridge Boulevard
Schedule & Travel Impacts
- No further traffic impacts
Project Facts
- Cost: $791,000
- Contractor: Paonia Inc.
- Timeline: March - June 2019
- Locations: