Northeast Colorado Traffic Signal Upgrades

About the Project

Crews on this project will install the following traffic-control devices at 71 different locations across Kit Carson, Larimer, Lincoln, Logan, Morgan, Phillips, Weld and Yuma counties in Northeast Colorado:

  • Traffic signal controllers and controller cabinets
  • Preformed controller cabinet foundations
  • Conduit
  • Pull boxes
  • Ethernet switches
  • Power supplies
  • Service-meter cabinets
  • Ancillary items

Crews also will complete minor grading and concrete work at some of the locations.


Travel Impacts

  • Work may take several days to complete at some locations
  • Traffic impacts are expected to be minimal at most locations
  • Temporary traffic control measures (all-way stops, uniformed traffic control officers or flaggers) may be in use during signal outages

Project Facts

  • Cost: $1.74 million
  • Contractor: Paonia Inc.
  • Location: 71 separate locations across Kit Carson, Larimer, Lincoln, Logan, Morgan, Phillips, Weld and Yuma counties
  • Timeline: July to December 2018