Leetsdale Resurfacing | Mississippi Avenue to Colorado Boulevard
Project completed
Project Facts
- Cost: $3.72 million
- Contractor: Brannan Sand and Gravel
- Timeline: April to August 2020
- Location: CO 83 - Leetsdale Drive from Mississippi Avenue to Colorado Boulevard
About the Project
On April 6, crews will begin work on Leetsdale Drive between Mississippi Avenue and Colorado Boulevard. Work on this project will include asphalt removal, asphalt SMA, concrete sidewalk and curb ramp work, and roadway re-striping.
Proposed Work Schedule
- April – May: Crews will complete concrete work on curb ramps and sidewalks. Motorists can expect single lane daytime closures during this work.
- June – August: Crews will resurface Leetsdale Dr. Motorists can expect overnight closures during this work.
Traffic Impacts
- Motorists should expect single lane closures during work hours.
- Daytime lane closure hours for concrete work are Monday through Friday from 9 a.m. to 3 p.m.
- Nighttime lane closure hours for resurfacing work are Sunday night through Friday morning:
- Northbound: 8 p.m. to 6 a.m.
- Southbound: 7 p.m. to 6 a.m.
- There will be no speed reductions or oversize/overweight restrictions.