Sign Replacement on US 550, US 160 & CO 140 in La Plata & San Juan Counties
Project Facts
- Cost: $260,000
- Contractor: Work Zone Traffic Control, Inc.
- Timeline: May - August 2018
Crews on this project replaced 1,400 signs and signposts along the following highways in Southwest Colorado:
- US 550 between Durango and Silverton:
Work started near the west junction with US 160, MP 21, and continued through the city of Durango to MP 70.
- US 550 between the New Mexico border to the US 160 intersection
- US 160, from west of Durango to the US 550 intersection:
Work was completed between MP 79 to Farmington Hill.
- CO 140 between the New Mexico border and the US 160 intersection at Hesperus