I-76 Cable Rail Project - Wiggins to Brush
Project Complete!
The project is located in Region 4, in Morgan County. Project work includes the installation of high-tension cable barrier TL-3 and concrete mow strip, along with ABC Class 6 (Special) on I-76 between Mile points 72.0 and 91.1. All work is in the interstate median.
Project Benefits
- Reduce the severity of vehicle median crashes
- Help the safety of the driving public
Work Schedule:
- Construction will begin on July 31st
- Monday through Friday from 7 a.m. to 5 p.m.
- The project is anticipated to end in February 2024.
Traffic Impacts:
Motorists can expect the following impacts during the period of construction:
- Motorists are to follow directions from flaggers on site.
Project Facts
- Construction Cost: $7.5 Million
- Contractor: IHC Scott
- Timeline: July 2023 to February 2024
- Location: I-76
- Nearest Town/City: Wiggins to Brush
- Mile Point(s): 72 to 91
- County: Morgan