Project Facts
- Cost: $3.17 million
- Contractor: SEMA Construction
- Timeline: March 2021 to March 2022
- Location: I-70 at the Ward Road Exit and on Ward Road
About the Project
This was a safety and traffic operations improvement project located at Interstate 70 and Ward Road (Colorado Highway 72) in Jefferson County. The project included widening and overlay of pavement and on/off ramps, the installation of new ramp meters and signs, and the addition of permanent water quality features and improved access to the RTD Park n Ride.
Work Schedule
- Work is substantially complete
- Guardrail repairs on Ward Road/CO 72 are scheduled for mid to late January 2022
Traffic Impacts
- No current impacts exist