Project Facts

  • Cost: $2.63 Million
  • Contractor: Schmidt Construction Company
  • Timeline: May to August 2021
  • Location:  Various I-25 interchange locations and CO 115 at NORAD in Colorado Springs

About the Project

This project resurfaced interchange ramps in the Colorado Springs area, upgraded guardrail systems and placed new pavement markings. Several locations received new asphalt curb, slope and ditch paving.

Construction on this project is complete, and improves safety with smoother highway transitions and new guardrail.


Project Locations

  • I-25 and CO 115 Interquest Parkway (MM 153) 
  • I-25 at Briargate Parkway (MM 151)
  • I-25 at N. Academy Boulevard (MM 150)
  • CO 115 at NORAD Road/O-Connell Blvd (MM 43)