I-76 Concrete Panel Replacement west of Fort Morgan
Project Facts
- Cost: $818,000
- Contractor: ABCO Contracting Inc.
- Timeline: March - April 2020
- Location: Just east of Fort Morgan
About the Project
In March 2020, CDOT crews will begin replacing concrete panels on eastbound I-76 just west of Fort Morgan. ABCO Contracting, Inc was contracted for this one-month project which will was completed in April 2020.
Work Schedule
- Schedule will commence in March 2020
Traffic Impacts
- Impacts have not yet commenced.