I-70 Resurfacing West of Parachute

Project Facts

  • Cost: $5 million
  • Contractor: United Companies
  • Timeline: August to November 2018
  • Location:
  • On I-70 west of Parachute in Garfield County (mile points 68 to 74.74), just north of the Mesa County line
I-70 Resurfacing West of Parachute.jpg

Crews on this project will resurface a six-mile stretch of both directions of I-70, just west of Parachute, Colorado—from mile points 68 to 74.74.

The project team also will address upward swelling of the roadway (aka, heaving) that's occured in the area.