I-70 Resurfacing from 32nd Avenue to 44th Avenue

Project completed

Project Facts

  • Cost: $4.7 million
  • Contractor(s): SEMA Construction
  • Timeline: August 2017 to Summer 2018

In April 2018, crews began the second phase of this project, which will repair and repave deteriorated bridge decks and lanes on I-70 from 32nd to 44th avenues, over Ward Road. Work started on westbound I-70 over Clear Creek between the two avenues.

Once complete, this work will extend the lifespan of this stretch of roadway and create a smoother ride.


Schedule

  • Work hours: 8 p.m. to 5:30 a.m. Sundays through Thursdays
  • Expected completion: Summer 2018
  • All work is weather dependent, and the schedule is subject to change.

Travel Impacts

  • Expect single- and double-lane closures on westbound I-70.
  • There will be single-lane closures on Colorado Highway 58 during work hours.
  • CO 58, I-70 and the ramp from eastbound CO 58 to westbound I-70 will be closed.
  • We'll communicate closures via electronic road signs around the project area. Please go slow in the cone zone.