I-70 Exit 26 Ramp Improvements in Grand Junction
Project complete
Project Overview
In September 2019, crews on this project will begin modifications to the existing Diverging Diamond Interchange (DDI), located on I-70 west of Grand Junction at Exit 26. The goal of this project is to create better traffic flow and update the exit.
Specific improvements include:
- the addition of a third and dedicated left-turn lane to westbound I-70
- median removal
- concrete and asphalt paving
- concrete barrier
- striping
- traffic pole installation
- and new signage.
Planned Work Schedule
The planned project work schedule is Monday through Thursday from 7 a.m. to 7 p.m.
Project Facts
- Cost: To be announced
- Contractor: KSK, LLC
- Timeline: September to November 2019
- Location: On I 70 West of Grand Junction at Exit 26