I-25 Resurfacing South of Trinidad

Project Facts

  • Cost: $5.4 million
  • Contractor(s): APC Southern Contractors
  • Location: On I-25 from mile points 7.5 to 12.9 in Las Animas County
  • Timeline: April - September 2018

On Monday, April 2, crews began improving sections of I-25 at Raton Pass. Work is scheduled to be complete in September 2018.

This work will include:

  • resurfacing the road;
  • repairing a bridge; and
  • improving guardrail.

Schedule

  • Work hours: 7 a.m. to 7 p.m., Mondays through Fridays
  • No weekend work is currently anticipated.

Travel Impacts

  • From April 9-12, there will be 24-hour, 12-foot-width reduction on northbound I-25 at mile point 10.4. Concrete barrier will be in place as will a speed-limit reduction of 45 mph.
  • Expect work crews in and around the CDOT Port of Entry, south of Trinidad.
  • Allow for travel delays of up to 15 minutes due to traffic being reduced to one lane.
  • All business owners and residents will maintain access to their property, though it may be temporarily altered.