Grand Junction Ramp Upgrades on I-70 & CO 340

From November 2018 through March 2019, crews on this project will upgrade on-/off-ramps and curb ramps to comply with the Americans With Disabilities Act (ADA) at three locations:

I-70 and 24 Road (aka I-70Z)

Broadway (aka CO 340) and Rice Street

Pitkin Avenue and Ute Avenue (aka I-70B)

These improvements will also bring each ramp, and some gutters and sidewalks, into compliance with Public Right of Way Accessibility Guidelines (PROWAG) requirements.

Project Facts

  • Cost: $523,000
  • Contractor: KSK Construction
  • Timeline: November 2018 - March 2019
  • Location: at three intersections in Grand Junction:
    1. I-70 and 24 Road (I-70Z);
    2. Broadway (aka CO 340) and Rice Street; and
    3. Pitkin Avenue and Ute Avenue (aka I-70B)