Denver Metro Bridge Safety Improvements

Project Complete!

This project is located in Region 1 in several counties. This project included installing corrugated steel plates to the underside of the decks on three structures in the metro Denver area.


Work Schedule:

  • .Work is concluded

Traffic Impacts:

  • No further traffic impacts.

Project Facts

  • Cost: $1.58 million
  • Contractor: Structures, Inc
  • Timeline: September 2022 - February 2023
  • Location: CO 88 over Bear Creek & I-70 over Tennyson & US 6 over CO 121