Denver Metro Bridge Safety Improvements
Project Complete!
This project is located in Region 1 in several counties. This project included installing corrugated steel plates to the underside of the decks on three structures in the metro Denver area.
Work Schedule:
- .Work is concluded
Traffic Impacts:
- No further traffic impacts.
Project Facts
- Cost: $1.58 million
- Contractor: Structures, Inc
- Timeline: September 2022 - February 2023
- Location: CO 88 over Bear Creek & I-70 over Tennyson & US 6 over CO 121