CO 9 & US 6 in Dillon Resurfacing

Project complete

Project Facts

  • Cost: $11 million
  • Annual Daily Traffic: 31,000
  • Location:
    • CO 9, mile points 101.6 to 107.0
    • CO 6, mile points 208.7 to 210.7

Project Team

  • Contractor(s): APC Southern Construction Company, LLC

Project Overview

From Monday, April 24, 2017, to Thursday, Oct. 19, 2017, crews made improvements to Colorado Highway (CO) 9 and US Highway 6, near I-70 in Dillon.

Project work included:

  • roadway repaving;
  • installing ADA-compliant ramps;
  • installing sidewalks;
  • traffic loops; and
  • drainage improvements.

Phased Work

Phase 1 Work:

  • removing and replacing curbs and gutters along CO 9

Phase 2 Work:

  • excavations, followed by drainage improvements and paving operations

Phase 3 Work:

  • milling and overlay operations, allowing the asphalt to line up with the new concrete improvements