CO 74 Resurfacing from I-70 to County Road 65

Project Complete.

Project Facts

  • Cost: $2.9 million
  • Contractor: APC Construction, Co.
  • Timeline: May - late fall 2019
  • Location: CO 74 from I-70 to County Road 65 (mile points 0 to 1.94) in Jefferson County

Beginning in May 2019, crews will begin resurfacing an approximate two-mile stretch of Colorado Highway 74 from I-70 to County Road 65 in Jefferson County.

Other specific improvements include:

  • installing a waterproofing membrane;
  • removing and replacing expansion joints;
  • removing and replacing damaged curbs and gutters;
  • upgrading curb ramps to comply with Americans With Disabilities Act (ADA) standards;
  • adding signs and striping; and
  • completing bridge deck work on Rainbow Hill Road

Schedule & Travel Impacts

  • Work hours: 7 a.m. - 4 p.m. Mondays - Thursdays; 7 a.m. - 1 p.m. Fridays
    • Overnight and weekend work as necessary
  • Expect single-lane closures on CO 74.