CO 60 Bridge Replacement Over the South Platte River

Project completed

Project Facts

  • Cost: $6.4 million
  • Contractor: Hamilton Construction
  • Timeline: Oct. 2018 to April 2019
  • Location: CO 60 bridge over the South Platte River in Weld County

Project Overview

Crews on this project will remove and replace a bridge on Colorado Highway 60 over the South Platte River in Weld County. To accommodate construction, crews will reconfigure the road in a new horizontal alignment west of the existing structure.


Schedule & Travel Impacts

  • Crews will start work in early October, and completion will take an estimated 155 days (late April 2019)
  • Work hours: 7 a.m. to 5 p.m., Mondays through Fridays
  • Work is weather dependent and subject to change