CO 52 Reclamation and Overlay

Project Facts

  • Cost: $5.9 million
  • Contractor: Simon Contractors
  • Timeline: April 29 - July 2019
  • Location: CO 52 from mile points (MP) 95.777 to 111.569 in Morgan and Weld counties

The project  supports CDOT's Whole System - Whole Safety initiative.

Crews have restored a 12.5-mile section of CO 52 from New Raymer south, using a process known as full-depth reclamation and overlay (reconstructing flexible pavement using the existing material as the base for the new roadway surface).


Progress

  • Complete: Asphalt reclamation and paving
  • Current work: Shouldering
  • Final work: Adding roadway striping, signs and delineators

Schedule & Travel Impacts

  • No further traffic impacts