CO 145 Culvert Installation Near Telluride

Project complete

Project Background

Project Facts

  • Cost:
    $495,861

Project Team

  • Contractor(s):
    Kirkland Construction

From Wednesday, Sept. 6, through October 2017, crews installed a concrete culvert beneath Colorado Highway 145 near Telluride. Work took place seven miles north of the roundabout (between mile points 79.9 and 80.1), in Sawpit, Colorado.

Crews also conducted erosion control on the highway embankment before seeding and mulching.