CO 13 Reconstruction in Rio Blanco County
Project completed
Project Overview
The project is complete, as of December 2020; CDOT crews will return in the spring or summer, weather permitting, to restripe this section for passing zones. Restriping will take place in the Spring or Summer 2021.
Schedule
- This work was completed in two seasons
- The project began June 2019 and was suspended for the winter between November 2019 and April 2020
- Work was completed in December 2020
Project Overvicw
- Concrete reconstruction and minor widening
- Drainage upgrades, including three under-highway corrugated steel drain pipes that were replaced with concrete box culverts
- Embankment safety improvements
- Sight distance improvements
- Wildlife fencing
- New signing and striping
Project Facts
- Cost: $16.9 million
- Contractor: Scott Contracting, Inc.
- Timeline: June 2019 to December 2020
- Locations: Colorado Highway 13 north and south of Rio Blanco County Road 5, between mile points 16.06 and 20.77