C-470 Noise Wall and Trail Improvements
Project completed
Project Overview
Three goals were accomplished with this project:
- C-470 Noise Wall: Approximately 2,600 feet of noise wall was constructed along the Lucent westbound on-ramp to C-470
- I-25 Ramp: From the I-25 ramp to C-470, 288 tons of mill and fill was placed in the three travel lanes
- C-470 Trail Work: On C-470 between Santa Fe and Wadsworth the concrete was removed, the trail regraded and new concrete poured. A new pedestrian rail was also installed
Project Facts
- Cost: $3.5 million
- Contractor: Hamilton Construction Company
- Timeline: July to October 2020
- Location: Douglas, Jefferson and Arapahoe Counties
Proposed Work Schedule
- Work is complete
Traffic Impacts
- No further traffic impacts