C-470 and I-76 Ramp Signalization

Project completed

Project Facts

  • Cost: $3.8 million
  • Contractor: W.L. Contractors
  • Timeline: March 2019 to March 2020
  • Location: On C-470 from Alameda Parkway to Wadsworth Boulevard, and on I-76 from Wadsworth Boulevard to Pecos Street

About the Project

From March 2019 through March 2020, crews on this project will place signals at on-ramps at C-470 from Alameda Parkway to Wadsworth Boulevard, and on I-76 from Wadsworth Boulevard to Pecos Street. These ramp meters will better manage traffic congestion on both roads.


Traffic Impacts


Expect shoulder closures and single-lane closures on the C-470 and I-76 on-ramps.