I-25 between 6th Avenue and 23rd Avenue
-
39.7389898615 -105.01404047
| Project Owner | CDOT |
| CDOT Region | 6 |
| County | Denver |
| Description of Work | Resurfaces approximately three miles of I-25 in asphalt. |
| Estimated Total Project Cost | $4,259,920 |
| ARRA Funds | $4,190,706 |
| Project Status | Under Construction- In winter shutdown |
| Start Date | June 14, 2009 |
| Completion Date | April 2010 |
| Percentage Spent | 76% |
| Contractor | Brannan Sand and Gravel Co. |