US 24 west of Limon

Project Owner CDOT
CDOT Region 1
County Elbert
Description of Work Resurfaces 10.8 miles of US 24 in asphalt.
Estimated Total Project Cost $6,851,078
ARRA Funds $6,717,078
Project Status Completed
Start Date May 2010
Completion Date August 2010
Percentage Spent N/A
Contractor APC Southern Construction Co.