US 36 between Estes Park and Lyons
-
40.3016543474 -105.383906364
Project Owner | CDOT |
CDOT Region | 4 |
County | Boulder and Larimer |
Description of Work | Chip seals 22 miles of US 36 to improve the roadway surface condition. |
Estimated Total Project Cost | $1,679,863 |
ARRA Funds | $1,652,568 |
Project Status | Construction Complete |
Start Date | August 3, 2009 |
Completion Date | September 2009 |
Percentage Spent | 100% |
Contractor | United Companies |