US 160 between Shaw Creek and Del Norte
-
37.6745818046 -106.398639679
Project Owner | CDOT |
CDOT Region | 5 |
County | Rio Grande |
Description of Work | Resurfaces three miles of US 160 in asphalt. |
Estimated Total Project Cost | $1,683,648 |
ARRA Funds | $1,656,292 |
Project Status | Construction Complete |
Start Date | October 5, 2009 |
Completion Date | November 2009 |
Percentage Spent | 100% |
Contractor | Elam Construction Co. |