Project Owner | CDOT |
CDOT Region | 6 |
County | Jefferson |
Description of Work | Resurfaces approximately three miles of US 40 in asphalt. |
Estimated Total Project Cost | $3,392,313 |
ARRA Funds | $3,337,195 |
Project Status | Construction Complete |
Start Date | June 1, 2009 |
Completion Date | September 2009 |
Percentage Spent | 100% |
Contractor | Asphalt Paving Co. |