State Highway 60 at I-25 in Johnstown
-
40.3352917633 -104.980201721
Project Owner | CDOT |
CDOT Region | 4 |
County | Weld |
Description of Work | Installs a new traffic signal at this intersection. |
Estimated Total Project Cost | $501,532 |
ARRA Funds | $493,383 |
Project Status | Construction Complete |
Start Date | August 31, 2009 |
Completion Date | November 2009 |
Percentage Spent | 100% |
Contractor | W.L. Contractors, Inc. |