I-25 Through Trinidad

 

Project Owner CDOT
CDOT Region 2
County Las Animas
Description of Work Constructs the Purgatoire River Pedestrian Trail, adds street lights, parking lot paving, curb and gutter, drainage inlets, landscaping and sidewalk. This work will be added onto the existing contract for work taking place on I-25 through Trinidad.
Estimated Total Project Cost $82.3 million
ARRA Funds $7,044,806
Project Status Under Construction
Start Date December 2006
Completion Date July 2011
Percentage Spent
Contractor Lawrence Construction Co.