I-70 between Pena Boulevard and Tower Road
-
39.7656655076 -104.790773392
Project Owner | CDOT |
CDOT Region | 6 |
County | Adams |
Description of Work | Installs median cable guardrail to prevent crossover accidents. |
Estimated Total Project Cost | $334,060 |
ARRA Funds | $328,632 |
Project Status | Construction Complete |
Start Date | July 20, 2009 |
Completion Date | August 2009 |
Percentage Spent | 100.00% |
Contractor | Ideal Fencing Corp. |