Tentative Schedule (All Dates are Subject to Change) |
|
Issue Letter of Interest |
April 12 – May 3, 2012 |
Value Engineering Study |
January 16-20, 2012 |
Project Briefings |
Ongoing |
Letter of Interests Due |
May 10, 2012 |
Issue Request for Qualifications (RFQ) |
May 17, 2012 |
Deadline for Submitting RFQ Questions |
May 31, 2012 |
CDOT Response to RFQ Questions |
June 13, 2012 |
Final RFQ Addendum Issued |
June 20, 2012 |
I-25 Re-Evaluation Complete |
Late April – Early May, 2012 |
Statement of Qualifications (SOQ) Due |
July 11, 2012 |
Evaluation of SOQ's Complete/Short List |
July 12-20, 2012 |
Notify Short Listed Submitters |
July 25, 2012 |
Issue Draft RFP to Short List |
July 30, 2012 |
Industry Review of Draft RFP |
August 20-24, 2012 |
CDOT Modifies Draft RFP |
August 27-31, 2012 |
CDOT Issues FINAL RFP |
September 5, 2012 |
TA & AC Meetings |
October 1-5, 2012 |
Submitters TA’s & AC’s Due |
October 12, 2012 |
CDOT Response to TA’s & AC’s |
October 19, 2012 |
PMJM BA/BO |
October 1, 2012 |
Final Proposals are Due |
November 16, 2012 |
Evaluate Proposals and Awards Contract |
November 19-27, 2012 |
Notice to Proceed |
December 18, 2012 |
Substantial Completion Date |
December 31, 2014 |