Tentative Schedule

Tentative Schedule (All Dates are Subject to Change)

Issue Letter of Interest

April 12 – May 3, 2012

Value Engineering Study

January 16-20, 2012

Project Briefings

Ongoing

Letter of Interests Due

May 10, 2012

Issue Request for Qualifications (RFQ)

May 17, 2012

Deadline for Submitting RFQ Questions

May 31, 2012

CDOT Response to RFQ Questions

June 13, 2012

Final RFQ Addendum Issued

June 20, 2012

I-25 Re-Evaluation Complete

Late April – Early May, 2012

Statement of Qualifications (SOQ) Due

July 11, 2012

Evaluation of SOQ's Complete/Short List

July 12-20, 2012

Notify Short Listed Submitters

July 25, 2012

Issue Draft RFP to Short List

July 30, 2012

Industry Review of Draft RFP

August 20-24, 2012

CDOT Modifies Draft RFP

August 27-31, 2012

CDOT Issues FINAL RFP

September 5, 2012

TA & AC Meetings

October 1-5, 2012

Submitters TA’s & AC’s Due

October 12, 2012

CDOT Response to TA’s & AC’s

October 19, 2012

PMJM BA/BO

October 1, 2012

Final Proposals are Due

November 16, 2012

Evaluate Proposals and Awards Contract

November 19-27, 2012

Notice to Proceed

December 18, 2012

Substantial Completion Date

December 31, 2014