Bridge Repairs in Denver, Adams, Jefferson & Clear Creek Counties

Project complete

Project Overview

In February 2019, crews began repairing nine bridges in Denver, Adams, Jefferson, and Clear Creek counties. Work includes:

  • repairing bridge bearings;
  • repairing abutments and rails;
  • sandblasting;
  • painting and sealing;
  • repairing paved slopes;
  • removing debris;
  • repairing anchor bolts and spalls;
  • reinforcing embankments; and
  • providing new access points to girders after removing trash and organic waste.

Project Facts

  • Cost: $1.4 million
  • Contractor: Hamilton Construction
  • Timeline: February to November 2019
  • Locations: Clear Creek, Jefferson, Adams and Denver counties