23rd Lane Storm Sewer (US 50C to Everett Road)

Project completed

About the Project

Crews have completed the storm sewer installation on 23rd Lane between US 50C and Everett Road in Pueblo. This work included the installation of new storm sewer, work on inlets and manholes, as well as asphalt and concrete patching on US 50C.

This project was Phase I of larger improvements scheduled on 23rd Lane. Phase II and III will commence after this project is complete and will include water line work and asphalt paving, respectively (by Water District and Pueblo County).

Specific improvements included:

  • Installation of new storm sewer
  • Work on inlets and manholes
  • Asphalt and concrete patching on US 50C.

Work Schedule

No further work scheduled

Project Facts

  • Cost: $1.6 million
  • Contractor: Tony J. Beltramo & Sons, Inc.
  • Timeline: January to May 2020
  • Location:  23rd Ln Storm Sewer (US 50C to Everett Road), Pueblo County