Military Access, Mobility & Safety Improvement Program Updates for Week of November 24, 2024

Travel Advisory

Nov. 22, 2024 - Nighttime Interstate 25 north- and southbound alternating lane closures at South Academy Boulevard to finish roadway work

Colorado Springs —­­­­ The Colorado Department of Transportation has scheduled alternating lane closures on Interstate 25 at South Academy Boulevard on Monday, Nov. 25 and Tuesday, Nov. 26 as crews perform concrete profiling work on the MAMSIP I-25 Safety and Efficiency Improvements project.

There will be north- and southbound alternating lane closures at South Academy Boulevard on Monday, Nov. 25 and Tuesday, Nov. 26, 7 p.m. to 5 a.m.

To help minimize potential traffic delays, CDOT is suspending work from midday Wednesday, Nov. 27 until Monday, Dec. 2. The only exception is for emergency operations.


El Paso County – MAMSIP – South Academy Boulevard Widening Project

Colorado Springs The southbound South Academy Boulevard off-ramp to Coventry Drive will be temporarily closed on Monday, Nov. 25 at 8 a.m. through Wednesday, Nov. 27, at 10 a.m. to allow crews to install new soundwall panels near the roadway. A detour will be in place:

Traffic intending to enter Coventry Drive from southbound South Academy Boulevard will continue east to Venetucci Boulevard, travel north to B Street and turn east onto E. Las Vegas Street (CanAm Highway), turn south onto Maxwell Street and turn onto Coventry Drive.

Detour map for closure at southbound South Academy Boulevard off-ramp to Coventry Drive.jpg
Detour map for closure at southbound South Academy Boulevard off-ramp to Coventry Drive

The northbound I-25 off-ramp lanes at South Academy Boulevard shifted onto new temporary alignment are ongoing to allow crews to install utilities and drainage across the roadway. This new alignment is scheduled to be in place until Dec. 2.

A shift of east- and westbound South Academy Boulevard between I-25 and Fountain Creek towards the center is ongoing to allow crews to work on the outside lanes, install drainage pipes, and prepare to construct a noise barrier. This alignment will be in place approximately until spring 2025.

Motorists are also advised that the shift of the northbound I-25 off-ramp to northbound South Academy Boulevard to a new alignment is ongoing and will have a short acceleration lane.

Motorists are advised to use caution at all entrance ramps as merge lengths have been shortened. In particular, motorists should be prepared to stop on the US 85/87 on-ramp to eastbound South Academy and the Bradley Road on-ramp to eastbound South Academy since merge area is greatly reduced.

All lanes of Bradley Road under South Academy Boulevard are shifted to the center of the roadway ongoing to allow crews to perform work on new bridge piers.

These closures are weather dependent and subject to change.


Traffic Impacts

I-25 between US 85/Fountain (MP 127) and South Academy Boulevard (MP 135) 

  • Alternating lane closures on north- and southbound I-25 over South Academy Boulevard, Monday, Nov. 25 and Tuesday, Nov. 26, 7 p.m. to 5 a.m.

South Academy Boulevard Widening Project

  • The southbound South Academy Boulevard off-ramp to Coventry Drive will be temporarily closed on Monday, Nov. 25 at 8 a.m. through Wednesday, Nov. 27, at 10 a.m.
  • The northbound I-25 off-ramp lanes at South Academy Boulevard shifts to temporary alignment Saturday Nov 23 and will be ongoing through Dec. 14.
  • Ongoing shift of east- and westbound South Academy Boulevard between I-25 and Fountain Creek to middle until spring 2025
  • Ongoing full closure of existing north- and southbound South Academy Boulevard on-ramps from US 85/87 and shift to temporary on-ramp, in place until fall 2024
  • Ongoing shift of all lanes on Bradley Road under South Academy Boulevard bridge

Project Overview

Interstate-25 – Safety and Efficiency Improvements

The improvements to I-25 addressed in this project are located along an approximately 7.5-mile segment of south I-25 beginning at South Academy Boulevard and extending to the Santa Fe Avenue (US 85/87) exit at Fountain (MP 128), which exits to Gate 19 of Fort Carson. The project includes:

  • Replacement of two bridges crossing over South Academy Boulevard
  • Widening of both inside and outside shoulders and installing safety improvements
  • Concrete surface treatment overlay to provide an improved riding surface
  • Installation of median barrier
  • Rehab and widening work on four bridges
  • Installation of an I-25 southbound deceleration lane at the interchange with CO 16

South Academy Boulevard Widening Project

The improvements to South Academy Boulevard in this project are located on South Academy Boulevard at the southern mile and a half of this arterial road from the I-25 interchange, crossing US Highway 85/87, and continuing to the road’s approach to Milton Proby Parkway (which connects to Powers Boulevard/CO 21). Construction focuses on widening an approximately 1.5-mile section of South Academy Boulevard from two lanes to three in each direction to alleviate recurring congestion. The project includes improved drainage facilities, lighting, striping, and expanded shoulders, modified merge lanes, sound walls and bridgework. The project is expected to be complete by early 2026. This project is managed by El Paso County.

Safety Benefits

CDOT conducted a safety assessment for the corridor to evaluate the magnitude and nature of safety problems and analyze the causes of crashes. These transportation improvements are mitigation measures to reduce crashes, improve infrastructure, and address physical deficiencies that contribute to crashes in the corridor. Over the next 20 years, the project is estimated to result in fewer deaths, injuries and crashes on the four MAMSIP corridors.

Project Contact Information

About the Military Access, Mobility & Safety Improvement Program Build Grant

Colorado Department of Transportation (CDOT) has initiated a program to deliver more efficient and safer mobility along I-25, Colorado Highway 94, South Academy Boulevard, and Charter Oak Ranch Road, enabling economic stability and development. The Military Access, Mobility & Safety Improvement Program is partially funded through an $18 million BUILD grant award from the US Department of Transportation. The delivery of these improvements will strengthen and enhance the redundancy of strategic movement between the nationally significant El Paso County military installations of Fort Carson, Peterson Space Force Base, Cheyenne Mountain Space Force Station, and Schriever Space Force Base.

Know Before You Go

Travelers are urged to “know before you go.” Gather information about weather forecasts and anticipated travel impacts and current road conditions prior to hitting the road. CDOT resources include:

Remember: Slow For The Cone Zone

The following tips are to help you stay safe while traveling through maintenance and construction work zones.

  • Do not speed in work zones. Obey the posted speed limits.
  • Stay Alert! Expect the unexpected.
  • Watch for workers. Drive with caution.
  • Don't change lanes unnecessarily.
  • Avoid using mobile devices such as phones while driving in work zones.
  • Turn on headlights so that workers and other drivers can see you.
  • Be especially alert at night while driving in work zones.
  • Expect delays, especially during peak travel times.
  • Allow ample space between you and the car in front of you.
  • Anticipate lane shifts and merge when directed to do so.
  • Be patient!

Download the COtrip App!

The new free COtrip Planner mobile app was designed to meet the growing trend of information on mobile and tablet devices for the traveling public. The COtrip Planner app provides statewide, real-time traffic information, and works on mobile devices that operate on the iOS and Android platforms. Visit the Google Play Store (Android devices) or the Apple Store (iOS devices) to download!