Eagle County — Work is resuming this month on the Colorado Department of Transportation’s I-70 West Vail Pass Auxiliary Lanes project. Crews are mobilizing to the construction area and clearing snow from equipment. The project enters its third season with an early focus on the construction of the Mile Point 185 westbound I-70 bridge, among other improvements to Interstate 70. This year’s work will involve narrowed lanes and shoulders along I-70, lane closures and temporary traffic holds along the recreation trail. Starting May 1, rock-blasting work and light evening delays are also expected. During these short blasts, I-70 traffic and recreation trail users will be stopped in both directions for up to 30 minutes. The blasting and limited delays will be similar to successful blasting that took place on the project last summer. Motorists and stakeholder partners will be able to sign up for day-of notifications about blasting and travel delays. More information about the rock blasting is available below.
Foundation work for the new westbound I-70 bridge over Polk Creek at MP 185 began last year. Both I-70 bridges in this area will ultimately be rebuilt, but starting with the westbound bridge has several advantages. Building the westbound bridge to the north of the existing structure will allow the new eastbound bridge to also shift to the north. This will reduce the length of the eastbound bridge by more than half, saving time and money. Moving the eastbound bridge to the north will also move it further from Black Gore Creek, reducing its impact on the creek habitat. Crews are planning to set the new westbound bridge girders this spring.
Work to improve safety and operations on I-70 from the East Vail Exit at MP 180 to the Vail Pass Rest Area Exit at MP 190 began in 2021. The first construction season culminated with the opening of a new emergency truck ramp near MP 182. Last year’s work relocated a 2-mile section of the Vail Pass Recreation Trail, including two bridges to cross the trail over Black Gore Creek. This section of the trail between MPs 185 and 187 needed to be moved farther from I-70 to facilitate the addition of an eastbound I-70 auxiliary lane and the realignment of substandard curves. The new path segment will open along with the rest of the recreation trail for Memorial Day weekend.
Other work planned to start later this summer includes the construction of six wildlife crossings and fencing, the eastbound highway closure system at the MP 180 interchange, and initial work on the eastbound auxiliary lane from MP 185 to MP 190.
Traffic Impacts
This year’s work will involve narrowed lanes and shoulders along I-70, lane closures and temporary traffic holds along the recreation trail. Rock-blasting work is also expected this year. During these short blasts, I-70 traffic and recreation trail users will be stopped in both directions for up to 30 minutes.
For I-70:
- Eastbound I-70 will be closed at Exit 180 (East Vail interchange) during traffic holds
- Westbound I-70 will be closed at Exit 190 (top of Vail Pass interchange) during the traffic holds
- Highway traffic holds are estimated to take place once per day when blasting occurs
- Highway traffic holds are anticipated to last 30 minutes, though motorists should plan for additional delays due to the time required to clear held traffic
- Highway traffic holds will only occur Monday to Thursday
- Highway traffic holds will occur once in the evening, between 6 and 8 p.m., to minimize travel impacts and delays. The exact time of when holds begin will vary depending on the day
- There will only be one blasting operation per scheduled day
- Rock blasting and traffic holds can take place Monday-Thursday but are not allowed on weekends or holidays
For Vail Pass Recreation Trail:
- Westbound trail users will be held at the Black Lakes picnic site
- Eastbound trail users will be held approximately 3 miles up the 20-foot-wide path section, just before the cul-de-sac, about halfway up Vail Pass where the trail crosses under I-70
- Construction flaggers will stop trail traffic at those holding locations
- Trail traffic holds are estimated to take place once per day when blasting occurs
- Trail traffic holds are anticipated to last up to one hour and possibly longer
- Trail traffic holds will only occur Monday to Thursday
- Trail traffic holds will occur in the evening between 5 and 8 p.m. Trail users are strongly advised to avoid using the trail during this time
- There will only be one blasting operation per scheduled day
- Rock blasting and trail traffic holds can take place Monday to Thursday but are not allowed on weekends or holidays
Shrine Pass Road
- Shrine Pass Road will be closed during blasting activities to ensure no one uses this road as a detour. The road is located at the top of Vail Pass.
Vail Pass Rest Area
- The Vail Pass Rest Area continues to be closed through October 2023 for reconstruction. Drivers can use exit 190 (Vail Pass), but there will not be restroom facilities available. CDOT encourages motorists to use other rest areas nearby, including the Gateway Visitor Center in Georgetown and the Edwards Rest Area in Edwards.
Blasting Information
Beginning Monday, May 1, crews will conduct periodic rock blasting work in the evening. Blasting work is allowed once a day between 6 and 8 p.m. CDOT anticipates four days of blasting within a two-week period. The project has the ability to conduct blasting up to 10 days, if needed. During evening blasting work, there will be evening traffic holds of up to 30 minutes for travelers on I-70 and the Vail Pass Recreation Trail. Motorists should anticipate one traffic hold and delays on evenings when rock blasting work takes place. Delays are also anticipated to be light, based on results during successful blasting in August 2022. Blasting work can take place Monday to Thursday but is not allowed on weekends or holidays.
To sign up for email alerts about the project's rock-blasting schedule for the week ahead, please sign up at subscription.cotrip.org/alerts/construction. Enter your email address and then select the Northwest Colorado region and choose I-70 Mountain Corridor | West Vail Pass Auxiliary Lanes. On days when blasting is scheduled, the project will send an update including any day-of schedule changes. The goal of these updates is to give travelers on I-70 as much notice as possible. Customers can also sign up for updates by contacting the project team at [email protected] or 970-688-8233.
The first traffic hold and subsequent blasting are scheduled to occur on Monday, May 1, between 6 p.m. and 8 p.m. Rock blasting is necessary to construct 2 miles of the new Vail Pass Recreation Trail on the west side of Vail Pass, between MP 185 and 187. Motorists are strongly encouraged to use COtrip.org to be prepared for traveling through this and other construction projects on the I-70 corridor. The Vail Pass Recreation Trail will also be significantly affected, please see below for more information.
Project Information
For additional information about this project:
- Call the project information line at 970-688-8233
- Email the project team at: [email protected]
- Visit the project website at: codot.gov/projects/i70westvailauxiliarylanes
Know Before You Go
Travelers are urged to “know before you go.” Gather information about weather forecasts and anticipated travel impacts and current road conditions prior to hitting the road. CDOT resources include:
- Road conditions and travel information: COtrip.org
- Download the COtrip Planner app: bit.ly/COtripapp
- Sign up for project or travel alerts: bit.ly/COnewsalerts
- See scheduled construction lane closures: bit.ly/laneclosures
- Connect with @ColoradoDOT on social media: Twitter, Facebook, Instagram and YouTube
Remember: Slow For The Cone Zone
The following tips are to help you stay safe while traveling through maintenance and construction work zones.
- Do not speed in work zones. Obey the posted speed limits.
- Stay Alert! Expect the unexpected.
- Watch for workers. Drive with caution.
- Don't change lanes unnecessarily.
- Avoid using mobile devices such as phones while driving in work zones.
- Turn on headlights so that workers and other drivers can see you.
- Be especially alert at night while driving in work zones.
- Expect delays, especially during peak travel times.
- Allow ample space between you and the car in front of you.
- Anticipate lane shifts and merge when directed to do so.
- Be patient!
Download the COtrip App!
The new FREE COtrip Planner mobile app was designed to meet the growing trend of information on mobile and tablet devices for the traveling public. The COtrip Planner app provides statewide, real-time traffic information, and works on mobile devices that operate on the iOS and Android platforms. Visit the Google Play Store (Android devices) or the Apple Store (iOS devices) to download!