April 27, 2018 - Southeastern Colorado/CDOT Region 2

Colorado Springs – This week there will be lane restrictions on Interstate-25 (I-25) between Northgate and Interquest Parkway Interchanges for temporary realigning of I-25 for culvert work at the Monument Creek Branch. Speeds have been reduced to 60 mph in this area.  These restrictions include:

Sun., Mon., and Tues., April 29, 30 and May 1 -- Overnight Lane Restrictions on I-25 for Traffic Shift

  • Double lane restrictions on southbound I-25 between Northgate and Interquest Parkway interchanges (milepost 154 – 156) for striping of southbound traffic switch. Traffic will be shifted to the right with reduced lane widths. There will be only one lane open.

    • Sunday night, April 29, 9 p.m. to 5 a.m.

  • Double lane restrictions on northbound and southbound I-25 between Interquest Parkway and Northgate interchanges (milepost 154 – 156) for striping of northbound traffic switch and to place temporary barrier on southbound I-25. Traffic will be shifted to the right with reduced lane widths. There will be only one lane open.

    • Monday night, April 30, 9 p.m. to 5 a.m.

  • Double left lane restrictions on northbound I-25 between Interquest Parkway and Northgate interchanges (milepost 154 – 156) to set temporary barrier on northbound I-25. Traffic will be shifted to the right with reduced lane widths. There will be only one lane open.

    • Tuesday night, May 1, 9 p.m. to 5 a.m.

Construction schedules are subject to change based on weather/unforeseen circumstances.

PROJECT INFORMATION: The Colorado Department of Transportation (CDOT) has initiated a project at the Monument Creek Branch under I-25 northbound and southbound lanes between Northgate and Interquest Parkway Interchanges to repair the box culverts (MP 154.9 and MP 155.0). The soil throughout this area is highly susceptible to erosion.

Storm flooding in 2013 and 2015 overwhelmed existing riprap in the channel and created several new channels. The channel in the 350 foot wide median between the structures was significantly degraded and the box culverts were significantly scoured. The runoff collected within the roadway sag of the I-25 southbound lanes, overtopped the asphalt curb and eroded a large area of the west side roadway embankment of I-25. The guardrail was also undermined by the erosion.

Project activities include:

  • Concrete box culvert and wingwall repairs

  • Construction of concrete drop structures to prevent future failures

  • Channel Armoring with boulders, riprap and grouted riprap

  • Placement of embankment material to restore the Monument Creek Branch channel and surrounding areas

  • Seeding of disturbed areas

  • Prebbles Meadow Jumping Mouse habitate allowances

For updated project information call 719-396-5585 or email [email protected]. For information regarding CDOT projects statewide, log on to www.codot.gov

Updates are also available via Twitter @coloradodot and be sure to “Like” our Facebook page at www.facebook.com/coloradodot