Crews Finish Paving US 550 Between Montrose & Ridgway

April 20, 2018 - Work completed one day ahead of schedule


SOUTHWEST COLORADO—
On Thursday, April 19, CDOT finished paving and striping US Highway 550 between Montrose and Ridgway. The work took three days and was completed one day ahead of schedule.

The roadway paving addressed an aged and damaged stretch of US 550 just north of the Ridgway Reservoir, from mile points 113 to 115.

THANK YOU: The CDOT Ridgway Maintenance Patrol thanks the traveling public, residents along the corridor, and the communities of Ridgway and Montrose for their patience during construction. CDOT also thanks the Colorado State Patrol for its presence and ensuring safety in the project work area.

Paving US 550 from Montrose - Ridgway
US 550 Montrose - Ridgway