CDOT to Repair Cracks on Three Highways in Southwest Colorado
April 19, 2018 -
SOUTHWEST COLORADO—On Monday, April 23, CDOT will start a road-repair project on portions of US Highway 550, and Colorado highways 184 and 141. Crews will place a heated crack sealant into cracks on these highways over several weeks to prolong the life of each road.
Dates |
Highway |
County/
|
Location
|
April 23-25 | US 550 Durango | La Plata County | 28.20–37.30 |
April 26-May 2 | CO 184B | Mancos & Montezuma counties | 8.9-26.6 |
May 3-4 | US 550 Ridgway | Ouray County | 107-113 |
May 7-10 | CO 141 (Nucla/Naturita) | Montrose County | 74-88 |
Travel Impacts
- Expect alternating, one-lane traffic, with delays of up to 10 minutes.
- Work hours are from 7 a.m. to 7 p.m., Monday through Friday.
- Please follow work zone signage, use caution, consider work safety, and be patient and safe.
Stay Informed