Full Overnight Closures of Cimarron Street/US 24 and Southbound I-25
These temporary, short-term closures include:
Full Overnight Closure of US 24/Cimarron Street and I-25 Ramps
Overnight closure of eastbound and westbound US 24/Cimarron Street between S. Sierra Madre and 8th streets for signal work, paving and painting operations.
-
Monday, Aug. 14 through Thursday, Aug. 17, 8 p.m. to 5 a.m. nightly. All I-25 ramps at Cimarron Street/US 24 will be closed.
-
Friday, Aug. 18, 9 p.m. to 5 a.m. US 24/Cimarron Street closed under I-25. All I-25 ramps at Cimarron Street/US 24 will remain open.
Full Overnight Closure of Southbound I-25
Overnight closure of southbound I-25 between Bijou Street and Tejon Street/Nevada Avenue for paving.
-
Tuesday, Aug. 15 and Wednesday, Aug. 16, 9 p.m. to 5 a.m. each night.
-
Single lane restrictions will begin at 7 p.m.
Overnight Lane Restrictions
Northbound and southbound I-25 left lane restrictions between Bijou Street and Tejon Street/Nevada Avenue for paving work.
-
Monday, Aug. 14, 7 p.m. to 5 a.m.
-
Tuesday, Aug. 15, 7 p.m. to 5 a.m. Northbound I-25 left lane restriction only.
Detour Information for the week of Aug. 13:
-
Detour Map - Monday, Aug. 14 and Thursday, Aug. 17 - Attached
-
Detour Map - Tuesday, Aug. 15 and Wednesday, Aug. 16 - Attached
-
Detour Map - Friday, Aug. 18 - Attached
Daytime Lane Restrictions
Various single lane closures on eastbound and westbound US 24/Cimarron Street between 8th and S. Sierra Madre streets.
-
Monday, Aug. 14 through Friday, Aug. 18, 9 a.m. to 3 p.m. daily.
Construction schedules are subject to change based on weather/unforeseen circumstances and schedule changes.
Drivers are Urged to Slow Down and Pay Attention
-
Speed reduction to 55 mph on I‐25 between South Nevada Avenue/Tejon Street and Cimarron/US24 (northbound and southbound)
-
Speed reduction to 45 mph on I‐25 from Cimarron/US24 to Bijou Street (northbound and southbound)
-
Speed reduction to 30 mph on US 24/Cimarron Street between 8th Street and I‐25 (westbound and eastbound)
-
Pay close attention when driving near the I‐25/Cimarron Project.
-
Slow down, observe speed limits, avoid distractions, and allow extra time for your commute.
-
Alternative route advised.
All Media Personnel: The I-25/Cimarron project is an active construction area. Access on the project site is restricted unless accompanied by a Colorado Department of Transportation or Kraemer representative. Your safety is important to us so please coordinate access requests in advance with Michelle Peulen. A safe area for interviews, b-roll, etc., and a project team member will be designated for escort and will coordinate the appropriate Personal Protective Equipment. We appreciate your cooperation.
PROJECT INFORMATION: The $113 million I-25/Cimarron Interchange Design-Build Project involves rebuilding the I-25 interchange between Colorado Avenue on the north and South Nevada Avenue to the south, 8th Street on the west and the Cimarron Street over Fountain Creek bridge on the east. Improvements are intended to provide enhanced operations, correct existing safety and design deficiencies, and to serve the anticipated short- and long-term travel demands in this area. When complete, this will be a high-functioning interchange that safely handles more vehicles and enhances multi-modal travel for those using I-25, US 24/Cimarron Street and the trail system along Monument and Fountain creeks. Project completion planned for December 2017.
For updated project information, visit https://www.codot.gov/
-
Information about weekly lane closures is available at https://www.codot.gov/travel/
scheduled-lane-closures.html -
For information regarding CDOT projects statewide, log on to www.codot.gov