Periodic Ramp/Lane Closures at I-25/Santa Fe
Lane closures on northbound Santa Fe Avenue. Periodic full and partial ramp closures from:
- Northbound Santa Fe to northbound I-25
- Northbound I-25 to Santa Fe/Alameda Avenue
- Northbound Santa Fe to southbound I-25
Detours will be in place, as needed.
No work is scheduled overnight Friday and Saturday.
Background
This $24 million project began in June 2014 and is scheduled to be completed in winter 2016/2017. Phases 1.2 and 1.3 were combined as a bridge replacement project that replaced the structures on I-25 over Santa Fe Drive. This project is now complete.
The current phase focuses primarily on Santa Fe, Alameda and southbound Kalamath. It includes the new bridge over the South Platte River that carries southbound I-25 off-ramp traffic onto southbound Santa Fe Drive. In addition, Alameda will be widened through the Santa Fe Drive/Kalamath Street intersections.
This project is designed to enhance safety, help reduce congestion and improve mobility through this heavily traveled area of Denver.
Stay Informed
For updated project information, visit https://www.codot.gov/
For information on other projects, visit http://www.cotrip.org/