Work planned on SH 257 over Big Thompson River pushed to late summer
MILLIKEN – The permanent flood repair work planned to begin March 16 that would have closed the bridge over the Big Thompson River on State Highway 257, just south of the Mad Russian Golf Course, will be postponed until later this summer.
As work was being planned for the bridge, some issues around utilities in the area would have delayed the work to the point where the work could have been in jeopardy from the spring runoff, so CDOT decided to delay the project until after the high water recedes.
Neighbors and businesses will receive at least 30-day notice before the closure this summer.
Stay Informed:
The best way to stay up to date on project progress and impacts is to sign up for email and wireless (text) alerts. Go to CDOT’s website at www.coloradodot.info and click on the envelope in the talk bubble in the lower right corner of the page. Enter your information and choose “General News- Floods” under the “Colorado Flooding” list.
Visit the project website at https://www.codot.gov/
If you have questions or concerns, please leave a message on the project information line or send an email to the project email address below.
Project Information Line: 970-785-6161
Email: [email protected]