I-70 Twin Tunnels Weekly Traffic Advisory
Preparatory blasting also continues about every three days. Blast days and times will not be available until the day prior to, or the day of, the blasting operation and will be provided by calling the project hotline at (303) 327-4034 or by checking one of the sources listed below.
CDOT will implement the following lane closures; traffic slowing should be expected during daylight hours:
- Monday, March 11
o 6 p.m. to 6 a.m. Tuesday – all lanes closed eastbound; eastbound and westbound traffic reduced to a single lane through the westbound tunnel
- Wednesday, March 13
o 7 a.m. to 9 a.m. – right lane closed
o 9 a.m. to 1 p.m. – single, mobile lane closures for striping
- Friday, March 15
o 9 p.m. to 6 a.m. Saturday – all lanes closed eastbound; eastbound and westbound traffic reduced to a single lane through the westbound tunnel
The speed limit is reduced to 35 mph while the traffic lanes are reduced.
Adding a third lane to eastbound I-70 from east Idaho Springs to the bottom of Floyd Hill is part of CDOT’s strategy at reducing congestion along one of the state’s busiest corridors which, in turn, will improve gas mileage and air quality.
To receive project updates via e-mail, visit www.coloradodot.info and click on the cell-phone icon in the upper right-hand corner. The link takes you to a list of items you can subscribe to, includingI-70 West, Denver to Glenwood Springs. Updates also are available via Twitter @coloradodot and on CDOT’s Facebook page at www.facebook.com/coloradodot.
CDOT also has launched a new smartphone application to provide drivers with easier access to I-70 traveler information. It includes travel speeds and times, road conditions, incidents, road work; and feeds from CDOT's closed-circuit television cameras and alerts. Text CDOT to 25827 or download CDOT Mobile from your App store.