Bridge Deck Replacement in Boulder to Reduce Foothills Parkway to One Lane in Each Direction
BOULDER COUNTY — Tomorrow, Wednesday, October 24, the Colorado Department of Transportation (CDOT) will reduce Foothills Parkway (State Highway 157) to one lane in each direction as part of the bridge deck replacement at US 36 in Boulder. The lane closure will be in place 24 hours a day, seven days a week throughout the remainder of the project, which is scheduled for completion in spring 2013.
The existing bridge deck of Foothills Parkway over US 36 was built in 1971 and is in poor condition that warrants significant repairs. Deck replacement will also include tie-in-work to the existing highway on both sides of the bridge.
Work on the project will be split between daytime and nighttime hours to be determined each week. Daytime work will be between the hours of 7 a.m. and 4:30 p.m. Monday through Friday and nighttime work will take place from 9 p.m. until 5:30 a.m. Monday through Friday. Single lane closures will be implemented on Foothills Parkway and will be in place 24/7. Three weekend closures of Foothills Parkway, as well as overnight closures of US 36, are planned but exact dates are not known at this time.
Delays of up to 10 minutes should be expected throughout the project work zone and the speed limit is reduced on Foothills Parkway to 35 MPH 24/7, and on US 36 to 40 MPH during night closures. CDOT would like to remind motorists to obey all road signs and flaggers, and to drive Slow for the Cone Zone.
The $1.3 million project is contracted to Jalisco International, Inc.
To receive real-time updates about road conditions in your area, visitwww.coloradodot.info and click on the green cell phone icon in the upper right hand corner of the page. Information about weekly lane closures will be available at www.coloradodot.info/travel/scheduled-lane-closures.html. Updates are also available via Twitter @coloradodot and be sure to “Like” our Facebook page at www.facebook.com/coloradodot.