Upcoming Surface Improvements on Highway 24
Beginning on Monday, July 23, and continuing through Thursday, July 26, from 7 a.m. to 5 p.m., pilot cars will be alternating traffic at various locations on U.S. 24, beginning about 2 ½ miles east of the Wilkerson Pass summit and continuing east two miles. Delays up to 10 minutes should be expected. All work is weather permitting.
The road is being resurfaced with 1 ½ inches of asphalt, preventing surface deterioration and helping to preserve the road base.
Updated information regarding traffic impacts on this or other CDOT projects is available at www.coloradodot.info/travel/scheduled-lane-closures.html or by calling 511. To receive project updates via e-mail, visit www.coloradodot.info and click on the cell-phone icon in the upper right-hand corner. The link takes you to a list of items you can subscribe to, including Southwest Colorado.